Anglian Water Upcoming Improvement Work - Overstone

Anglian Water Upcoming Improvement Work - Overstone

July 2021 Update:

Anglian Water have reported that their team are making good progress. So far they have installed 1.2km of new water pipes. They are still on track to complete this project by the end of October 2021. They will be drilling their new pipe under the A43, and Holcot Road this week. Please see the map for their progress so far.

To ensure the safety of their workforce and the public, traffic management will continue to be in place until the end of the project; A43, 30mph speed restriction.